RESIDENTIAL PROJECT



EMIRA SERVICES APARTMENT, SHAH ALAM
Stages Involved: Contract Implementation and Management Phase, Final Completion Phases
Period: October 2017 - August 2018
Description:
Submit Amendment Building Plan to Majlis Bandaraya Shah Alam. Assist in submitting borang F to LAM. Collect all borang G from each consultants and contractor to submit for authority. Assist in issue architect instruction letter and interim certificate to main contractor. Involved in CPC inspections to produce defect list to main contractor.




NORRA CONDOMINIUM, DESA PARK CITY, KUALA LUMPUR
Stages Involved: Schematic Design Phase, Design Development Phase, Contract Documentation Phase
Period: April 2021 - September 2022
Description:
Prepare DO & ADO submission dwg to planning authority. Prepare DO & ADO refuse submission drawing to SW Corp, Coordinate with collaborative architects and consultants in authority compliances, ex: SW Corp, POS Malaysia compliances. Prepare tender drawings submission for tender bidding.




2 storey Auxiliary Police Hostel, Kuala Lumpur
Stages Involved: Schematic Design Phase
Period: October 2021 - September 2022
Description:
Prepare schematic design proposal, design brief according to space matrix and Neufert, design approaches, precedent study to clients
COMMERCIAL PROJECT



TANJUNG BALAI COMMERCIAL BUILDING, BANGSAR BARU, KUALA LUMPUR
Stages Involved: Contract Documentation Phase
Period: May 2018 - August 2018
Description:
Prepare documentation, architecture drawing for tendering stage. Assist in issue Letter of Award to Contractor. Submit Borang B to DBKL for the construction to start work on site.
INDUSTRIAL PROJECT
DATA CENTERS, KUALA LUMPUR
Stages Involved: Schematic Design Phases, Design Development Phases, Contract Documentation Phases, Contract Implementation and Management Phases, Final Completion Phases
Period: November 2022 - Current
Description:
- Prepare preliminary conceptual sketches proposal
- Prepare architectural drawing to submit Development Order (DO) for planning department and Building Plan (BP) building department
- Prepare & resubmit to local authority for amendment towards development order, DO and building plan, BP upon change of building design.
- Preparing architectural drawing in tender stages, prepare and evaluate tender report upon attending tender interview with clients, consultant and contractor.
- Assist in submitting start work permit to local authority
- Perform duties of superintending officer under building contract
- Prepare minutes & chaired meeting (site meeting, technical meeting & client consultants meetings), Issued Architect Instruction (AI), reply RFI and submission form to main contractor
- Issue Certificate of Non Completion, CNC when contractor unable to completed within contractual completion date.
- Access Extension of Time (EOT)
- Collect G Form & F Form with supporting documents, invite local authority for inspection to obtain letter of clearance. Deposited Certificate of Completion and Compliance, CCC to local authority.
- Prepare and check necessary drawings (As-Built Drawing), collect warranty and operational & manual, issued Certificate of Practical Completion, CPC upon building contractual completion.