EMIRA SERVICES APARTMENT, SHAH ALAM

Stages Involved: Contract Implementation and Management Phase

Period: October 2017 - August 2018

Description: 

Submit Amendment Building Plan to Majlis Bandaraya Shah Alam. Assist in submitting borang F to LAM. Collect all borang G from each consultants and contractor to submit for authority. Assist in issue architect instruction letter and interim certificate to main contractor. Involved in CPC inspections to produce defect list to main contractor.

TANJUNG BALAI COMMERCIAL BUILDING, BANGSAR BARU

Stages Involved:  Contract Documentation Phase

Period: May 2018 - August 2018

Description: 

Prepare documentation, architecture drawing for tendering stage. Assist in issue Letter of Award to Contractor. Submit Borang B to DBKL for the construction to start work on site.

Norra Condominium, DesaParkCity Kuala Lumpur

Stages Involved: Schematic Design Phase

Period: Apr 2021 - 2022

Description: 

Prepare DO & ADO submission dwg to planning authority. Prepare DO  & ADO refuse submission drawing to SW Corp, Coordinate with collaborative architects and consultants in authority compliances, ex: SW Corp, POS Malaysia compliances. Prepare Tender drawings submission.

2 storey Auxiliary Police Hostel, Kuala Lumpur

Stages Involved: Schematic Design Phase

Period: Oct 2021 - 2022

Description: 

Prepare schematic design proposal, design brief according to space matrix and Neufert, design approaches, precedent study to clients

EXSIM Data Center, Kuala Lumpur

Stages Involved: Schematic Design to Contract Management and Implementation Phase

Period: Nov 2021 - Current

Description: 

- Prepare preliminary conceptual sketches proposal.

- Prepare DO, BP, ADO, ABP to submit to authority.

- Prepare archtiectural drawing in tender stages, prepare and evaluate tender report upon attending tender interview with clients, consultant and contractor, assist in issue letter of award to contractor on behalf of clients

- Submit borang B and permit to start work to authority. prepare minutes, issue CNC, AI, RFI to contractor.

- Prepare  construction drawing for issuances.